Abu Dhabi Heavy-Vehicle Timings and Restricted Roads: 2026 Guide for Lowbed Trailer Moves

Lowbed trailer carrying heavy equipment in Abu Dhabi with a logistics worker checking route planning details

If you are moving an excavator, generator, crane component, oilfield skid, or other oversized asset through the capital, Abu Dhabi truck timings are not a small scheduling detail; they can decide whether your lowbed trailer move runs smoothly or gets delayed before it even reaches the site gate. In 2026, route planning for heavy vehicles in Abu Dhabi means checking two layers at the same time: the citywide heavy-vehicle timing restrictions and the newer road-specific restrictions affecting major corridors such as E10, E11, and parts of E30 in Musaffah.

That matters because lowbed trailer transport is rarely “just drive from A to B.” A lowbed move may involve oversize dimensions, axle-load checks, permit windows, bridge clearance, police instructions, site access slots, and coordination with project teams waiting for the equipment.

This guide breaks down the latest public rules, restricted roads, alternative routes, permit considerations, and practical planning steps so contractors, fleet managers, and logistics teams can plan safer, cleaner, and more predictable lowbed trailer moves across Abu Dhabi.

Key Takeaways

  • The official Abu Dhabi City heavy-vehicle restriction in 2026 is based on the Department of Municipalities and Transport’s Administrative Decision No. 5 of 2025: Monday to Thursday, heavy vehicles are banned from 6:30am to 9:00am and 3:00pm to 7:00pm; on Friday, the restricted periods are 6:30am to 9:00am and 11:00am to 1:00pm.
  • Heavy vehicles are also restricted on specific corridors. ITC/Abu Dhabi Mobility announced a heavy-vehicle ban on Sheikh Maktoum bin Rashid Road (E11) and Al Raha Beach Road (E10), plus peak-hour restrictions on Al Rawdah Road/E30 in the Musaffah area, according to the Emirates News Agency report on the ITC decision.
  • Lowbed trailer route planning should start with the cargo dimensions, weight, axle load, loading point, delivery point, timing window, permit status, and route restrictions—not with driver availability.
  • The UAE’s federal heavy-vehicle framework defines a heavy vehicle as land transport designed to carry goods with an empty weight exceeding 2.5 tons, and it places obligations on operators to manage weight, dimensions, distribution, and load fixing under the UAE heavy-vehicle weights and dimensions law.
  • For urgent or planned heavy equipment moves, contractors should use experienced operators who understand Abu Dhabi timing windows, restricted roads, lowbed trailer specifications, route checks, permits, load securement, and site coordination.

What Are Abu Dhabi Truck Timings in 2026?

Abu Dhabi truck timings are the restricted periods when heavy vehicles are not allowed to move on Abu Dhabi City roads. The core timing rule comes from the Department of Municipalities and Transport’s 2025 administrative decision regulating heavy-vehicle movement in Abu Dhabi City. The decision covers trucks, tankers, and heavy equipment, which makes it directly relevant for lowbed trailer operations carrying construction machinery, oilfield equipment, industrial cargo, and other large assets.

Here is the short version for planners: do not treat “morning” and “evening” as vague peak periods. The timing windows are specific, and a move planned even 15 minutes too close to a restricted period can create risk for dispatch, staging, or final delivery.

Day Restricted Morning Timing Restricted Later Timing Applies To
Monday to Thursday 6:30am–9:00am 3:00pm–7:00pm Heavy vehicles on Abu Dhabi City roads
Friday 6:30am–9:00am 11:00am–1:00pm Heavy vehicles on Abu Dhabi City roads

 

The timing schedule above is based on the official DMT heavy-vehicle movement decision, which states that heavy vehicles are banned during those periods and that the Integrated Transport Centre coordinates with Abu Dhabi Police to support compliance.

Why This Matters More for Lowbed Trailers

For a normal delivery truck, avoiding peak-hour restrictions may be inconvenient. For a lowbed trailer move, it can be the difference between a controlled transport plan and a domino effect of delays. A lowbed trailer may need:

  • A pre-approved route
  • A staging area outside restricted zones
  • Additional turning clearance
  • Escort coordination
  • Site crane or forklift availability
  • A time slot for loading and unloading
  • Confirmation that the cargo does not exceed legal or permit limits

If the trailer reaches a restricted area too late, the driver may need to wait at a safe holding point. That waiting period can disrupt site crews, equipment handovers, and project deadlines. For high-value machinery, the cost of delay is often higher than the transport cost itself.

Abu Dhabi Truck Restricted Roads: What Changed for Heavy Vehicles?

The timing windows are only one part of the 2026 planning picture. Abu Dhabi also has road-specific restrictions that affect heavy vehicles on key corridors. These restrictions are especially important for lowbed moves because many heavy equipment routes pass through industrial, logistics, construction, and port-linked areas.

According to the WAM report on ITC’s heavy-vehicle restrictions, heavy-vehicle movement is banned on Sheikh Maktoum bin Rashid Road (E11) and Al Raha Beach Road (E10), effective from December 1, 2025. The same announcement also notes that truck movement is prohibited during peak hours on Al Rawdah Road in the Musaffah area, from the bridges complex to the Sheikh Khalifa Bin Zayed International Road junction on E30, with an alternative route through the ICAD Bridge.

Road / Area Restriction Type Planning Impact for Lowbed Moves Alternative Mentioned Publicly
Sheikh Maktoum bin Rashid Road (E11) Heavy-vehicle ban Do not assume E11 is usable for heavy equipment movement without checking current route approval and signage Al Fayah–Seih Shuaib Road (E75) and Al Haffar Road
Al Raha Beach Road (E10) Heavy-vehicle ban Avoid routing lowbed trailer traffic through this corridor unless a valid authority-approved exception applies Al Fayah–Seih Shuaib Road (E75) and Al Haffar Road
Al Rawdah Road / E30 in Musaffah Peak-hour truck restriction Musaffah industrial moves need timing and route checks before dispatch ICAD Bridge route

 

Abu Dhabi Mobility later activated 24-hour heavy-vehicle permit processing for certain key routes, and companies can apply through TAMM, according to the Aletihad report on 24-hour permit issuance. For logistics planners, the takeaway is simple: do not rely on last year’s route template. In 2026, confirm the permitted route, restricted roads, signs, and timing window before the trailer leaves the yard.

Restricted Roads vs. Timing Restrictions: Do Not Mix Them Up

One common mistake is assuming that if a move happens outside the citywide restricted hours, every road becomes available. That is not how route planning should be handled. A road-specific ban can still apply even outside a general timing window, while a peak-hour road restriction can apply on top of the Abu Dhabi City timing rules.

Think of it as two filters:

  • Time filter: Is the move happening during a banned heavy-vehicle timing window?
  • Route filter: Does the selected road allow heavy vehicles, oversized loads, or lowbed trailer traffic under current rules and signage?

Only when both filters are clear should the move proceed.

What Counts as a Heavy Vehicle in the UAE?

For lowbed trailer operations, the legal definition matters because it affects compliance duties. Under the UAE’s federal heavy-vehicle law, a heavy vehicle is a land transport vehicle designed to transport goods with an empty weight exceeding 2.5 tons. The law also addresses axle weight, total weight, maximum gross vehicle weight, maximum dimensions, and operator obligations, including proper load distribution and fixing, as explained in the UAE legislation on heavy-vehicle weights and dimensions.

In practical terms, lowbed trailer planning should assume heavy-vehicle compliance applies when you are transporting:

  • Excavators, dozers, wheel loaders, graders, cranes, and compactors
  • Generators, compressors, transformers, tanks, and industrial skids
  • Oilfield service equipment, wireline units, pressure-control equipment, and rig-support assets
  • Oversized project cargo that may exceed standard width, height, weight, or turning limits
  • Heavy machinery moved from Musaffah, ICAD, Khalifa Industrial Zone, construction sites, ports, yards, or oilfield support bases

The legal definition is only the starting point. A lowbed trailer move can also trigger oversize-load considerations because the cargo may exceed standard road dimensions even when the vehicle itself is roadworthy.

Why Lowbed Trailer Route Planning Is Different from Normal Truck Planning

Lowbed trailers are designed for heavy and oversized cargo. Their lower deck height helps keep tall equipment within transport-height limits, but the complete vehicle-and-load combination still needs a route that can physically and legally handle it. If you want a deeper breakdown of deck height, axle configuration, and payload considerations, KhoCAR’s lowbed trailer specifications guide is a useful companion resource.

Lowbed moves are more complex because the planner has to consider several constraints at once:

Height and Clearance

The total transport height is not just the machine height. It is the trailer deck height plus the cargo height plus any supports, attachments, boom position, protective covers, and load-securing components. A route that works for an empty lowbed trailer may not work once an excavator or industrial unit is loaded.

Width and Turning Radius

Some heavy machines extend beyond standard lane width. Even when the route is legal, turning into a site entrance, industrial yard, or narrow access road can be the real challenge. A lowbed move should assess the full turning path, not just the road name.

Weight and Axle Load

Authorities often care about axle load as much as total weight because axle pressure affects bridges and road surfaces. A heavy machine placed incorrectly on the trailer can overload a rear axle group even when the total gross weight looks acceptable. The UAE federal framework specifically requires operators to avoid exceeding total and axial weights and to ensure loads are properly distributed and fixed, according to the heavy-vehicle operator obligations in UAE law.

Timing Windows

Lowbed moves usually take longer to load, secure, inspect, drive, enter the site, and unload. The safe dispatch window must include buffer time before the next restricted period begins. A plan that says “leave at 2:30pm” may be risky if the evening restriction starts at 3:00pm and the route passes into Abu Dhabi City.

Permit and Route Approval

Where heavy-vehicle movement permits are required, the permit conditions may define the route, timing, validity period, vehicle details, cargo details, and operational restrictions. TAMM’s heavy vehicle mobility permit service is the official starting point for permits related to truck passage on roads and prohibited areas.

Step-by-Step Lowbed Trailer Route Planning for Abu Dhabi

A good lowbed trailer move begins before the driver is assigned. The best planners build the route from the cargo outward.

Step 1: Confirm the Cargo Profile

Record the cargo details before checking the route:

  • Cargo type: excavator, loader, generator, transformer, oilfield skid, crane section, containerized unit, or other machinery
  • Length, width, and height
  • Operating weight and transport weight
  • Center of gravity
  • Attachment position, such as folded boom, bucket, blade, or counterweight
  • Tie-down points and securement method
  • Whether the machine can self-load or needs a crane/forklift/ramp support

Example: A 38-ton excavator with a folded boom may fit on a suitable lowbed trailer, but the same excavator with an attachment left installed may exceed height or rear overhang limits. That small detail can change the route and permit requirement.

Step 2: Match the Trailer to the Load

The selected lowbed trailer should match the cargo’s weight, dimensions, deck-height requirement, axle-load requirement, and loading method. If the cargo is tall, a lower deck can reduce clearance risk. If the cargo is extremely heavy, more axles can distribute the weight better. If the cargo is long, an extendable or specialized trailer may be required.

KhoCAR’s lowbed trailer services in the UAE cover heavy machinery, industrial equipment, oversized loads, and route coordination for projects across Abu Dhabi, Dubai, Sharjah, and other Emirates.

Step 3: Check the Timing Window

For Abu Dhabi City movements, compare the planned move time against the official timing restrictions:

  • Monday to Thursday: avoid 6:30am–9:00am and 3:00pm–7:00pm
  • Friday: avoid 6:30am–9:00am and 11:00am–1:00pm

Then add a realistic buffer. Do not schedule a lowbed trailer to enter a controlled area minutes before a restriction begins. Loading delays, gate checks, slow turns, roadworks, or police instructions can turn a “legal” plan into a blocked one.

Step 4: Check Restricted Roads and Alternative Corridors

Review road-specific restrictions for E10, E11, E30, Musaffah, and any corridor near the pickup or delivery site. The public ITC announcement identified E75 and Al Haffar Road as alternatives for heavy vehicles affected by the E10/E11 restrictions, and ICAD Bridge as the alternative for the Al Rawdah Road/E30 Musaffah restriction during peak hours, as reported by WAM on the ITC heavy-vehicle ban.

Use route tools such as Darbi’s Abu Dhabi map and journey planner to review traffic conditions and road information, but remember that a map route is not the same as a heavy-vehicle approval. For a lowbed trailer, the approved heavy-vehicle route and permit conditions matter more than the fastest navigation result.

Step 5: Confirm Permit Requirements

If the move involves prohibited areas, restricted roads, oversize dimensions, unusual timing, or designated heavy-vehicle corridors, check whether a mobility permit is required through TAMM’s heavy vehicle permit service. Keep the permit available to the driver and operations coordinator.

For high-risk or time-sensitive projects, avoid applying at the last minute. Even when permit processing is available around the clock for certain routes, the operation still needs correct cargo information, vehicle details, route details, and internal coordination.

Step 6: Inspect the Site Access

Many delays happen at the last 500 meters, not on the highway. Before dispatch, check:

  • Site gate width and turning angle
  • Internal road surface and gradient
  • Overhead cables, gantries, pipe racks, and shade structures
  • Space for unloading and turning around
  • Ground-bearing capacity in yards or construction zones
  • Whether the site accepts heavy vehicles at the planned arrival time

Example: A lowbed trailer carrying a generator from Musaffah to a construction site may clear the main roads but struggle at the delivery gate if parked cars, temporary barriers, or narrow internal access roads were not checked.

Step 7: Build a Dispatch Timeline

The timeline should include:

  • Yard inspection and loading
  • Load securement
  • Driver briefing
  • Permit and document check
  • Departure time
  • Expected restricted-road avoidance points
  • Staging/holding point if needed
  • Arrival gate time
  • Unloading support
  • Return route for empty trailer

The return trip matters too. A lowbed trailer that delivers before a restriction window may still be empty and exposed to restricted timings on its way back.

Practical Timing Scenarios for Abu Dhabi Lowbed Moves

The following examples show how timing and route planning work in real life. These are planning examples only; final routes should always be checked against current authority instructions, signage, permits, and site requirements.

Scenario Risk Better Planning Approach
Lowbed pickup in Musaffah at 2:15pm on Tuesday for delivery inside Abu Dhabi City The 3:00pm–7:00pm Monday–Thursday restriction may interrupt movement before delivery Load earlier, stage safely, or schedule after the evening restriction depending on permit and site acceptance
Heavy equipment route originally planned via E11 E11 heavy-vehicle restrictions may apply Check current route approval and consider designated heavy-vehicle alternatives such as E75 or Al Haffar Road where applicable
Friday morning lowbed move to a project site 6:30am–9:00am restriction and 11:00am–1:00pm Friday restriction compress the available window Plan either a properly buffered mid-morning window or a later move after the second restricted period
Oversized load from an industrial yard to a coastal project area E10/Al Raha Beach Road restrictions may affect route choice Confirm whether the route is allowed, whether a permit is required, and whether an alternative corridor is needed

 

Permit and Document Checklist for Lowbed Trailer Moves

Lowbed trailer documentation should be prepared before the unit reaches the loading point. A missing document can delay the truck even when the trailer, driver, and equipment are ready.

Route and Permit Documents

  • Heavy vehicle mobility permit, if required
  • Approved route details, including roads to avoid
  • Timing window and permit validity
  • Any police, escort, or authority instructions
  • Pickup and delivery site access approvals

Vehicle and Trailer Documents

  • Vehicle registration details
  • Trailer registration and specification details
  • Insurance documents
  • Driver licence and authorization
  • Equipment fitness or inspection records, where applicable

Cargo Documents

  • Cargo description
  • Weight certificate or verified weight details
  • Length, width, and height
  • Lifting or loading method statement, where required
  • Tie-down plan or load-securing method
  • Owner/site contact details

Operational Documents

  • Driver briefing note
  • Emergency contact list
  • Site contact and gate instructions
  • Holding point plan
  • Weather and visibility check
  • Photo record of loaded cargo and tie-downs

This may feel like a lot of paperwork, but it protects the project. If a driver is stopped, rerouted, or asked to confirm cargo details, clear documentation can prevent confusion and downtime.

Common Mistakes That Delay Abu Dhabi Lowbed Trailer Moves

Mistake 1: Planning Around Distance Instead of Restrictions

The shortest route may not be the legal or practical route. In Abu Dhabi, a road that looks direct on a map may be restricted for heavy vehicles, unsuitable for an oversized load, or risky during peak windows.

Mistake 2: Ignoring Friday Timing Differences

Friday does not follow the same afternoon/evening timing pattern as Monday to Thursday. The Friday later restriction is 11:00am–1:00pm, not 3:00pm–7:00pm, based on the official Abu Dhabi City heavy-vehicle timing decision. That difference matters when moving equipment after morning site work or before prayer-hour traffic patterns.

Mistake 3: Treating the Permit as a Formality

The permit is not just a piece of paper. It may define the route, timing, and operating conditions. If the dispatcher changes the route without checking the permit, the move can become non-compliant.

Mistake 4: Forgetting the Empty Return Journey

Once the cargo is delivered, the trailer still has to move. Return timing should be checked against the same restrictions, especially if the unit must return through Abu Dhabi City, Musaffah, or restricted corridors.

Mistake 5: Not Checking Site Access

Site access can be the weak link in an otherwise good plan. Lowbed trailers need turning room, ground clearance, safe unloading space, and a clear path. Project sites should remove parked vehicles, temporary barricades, low-hanging cables, and loose material from the access route before the trailer arrives.

Mistake 6: Poor Load Distribution

Load distribution affects braking, steering, tire wear, axle limits, and safety. UAE heavy-vehicle legislation specifically requires operators to ensure proper distribution and stabilization of loads, as stated in the operator obligations under Federal Decree-Law No. 12 of 2023.

Lowbed Trailer Route Planning for Musaffah, ICAD, and Industrial Moves

Musaffah and ICAD are central to heavy equipment movement in Abu Dhabi. They contain industrial yards, workshops, fabrication facilities, logistics bases, repair centers, and equipment suppliers. That makes them common pickup and delivery points for lowbed trailers.

In 2026, Musaffah route planning needs careful attention because the E30/Al Rawdah Road restriction affects truck movement during peak hours in a specific area. The publicly announced alternative through ICAD Bridge is particularly relevant for heavy vehicles moving between industrial zones and larger corridors.

For Musaffah and ICAD moves, planners should ask:

  • Does the move enter Abu Dhabi City roads during restricted heavy-vehicle timings?
  • Does the route touch Al Rawdah Road/E30 near the restricted segment?
  • Is the cargo oversized enough to need an approved route?
  • Is the site gate accessible by lowbed trailer?
  • Is unloading allowed during the planned time window?
  • Is a holding point available if timing changes?
  • Is the return trip planned?

This is where experienced dispatch matters. A planner familiar with local industrial access can often prevent delays that a generic map route would never predict.

How to Build a Safer Lowbed Trailer Route Plan

Use this quick planning flow before every move:

  • Measure the cargo. Record weight, length, width, height, and center of gravity.
  • Select the trailer. Match payload, deck height, axle count, loading method, and securing points.
  • Check the legal category. Confirm whether heavy-vehicle, oversize, or permit rules apply.
  • Check Abu Dhabi truck timings. Avoid restricted time windows with a buffer.
  • Check restricted roads. Review E10, E11, E30/Musaffah, and any route-specific restrictions.
  • Confirm permit needs. Use TAMM where a heavy vehicle mobility permit is required.
  • Review route physically. Check bridges, turns, ramps, gates, cables, roadworks, and traffic notices.
  • Coordinate the site. Confirm loading/unloading crew, crane/forklift, security gate, and safe space.
  • Brief the driver. Share route, timing, permit, contact numbers, holding points, and contingency plan.
  • Document the move. Keep photos, inspection notes, permits, and delivery confirmation.

This process is slower than guessing, but it is faster than recovering from a rejected route, a missed permit condition, or a blocked site entrance.

What Contractors Should Ask Before Booking a Lowbed Trailer

Before booking, give the transport provider enough information to quote and plan correctly. The most useful questions are:

  • What exactly is being moved?
  • Where is the pickup point and delivery point?
  • What are the cargo dimensions and weight?
  • Is the cargo self-propelled or does it need loading equipment?
  • Are attachments installed or removed?
  • Is the cargo urgent, scheduled, or tied to a site shutdown?
  • Is the move within Abu Dhabi City, Musaffah, ICAD, another Emirate, or an inter-emirate route?
  • Are there restrictions at either site gate?
  • Is there an existing permit, or does one need to be arranged?

If a lowbed trailer provider gives a price without asking these questions, be careful. Heavy equipment transport is not a simple pickup job; it is a compliance and risk-management job.

How KhoCAR Helps with Lowbed Trailer Moves in Abu Dhabi and the UAE

KhoCAR supports contractors, industrial companies, construction teams, and oilfield operators that need safe lowbed trailer transport across Abu Dhabi and the wider UAE. The goal is not only to provide a trailer; it is to move heavy equipment with the right planning, timing, driver support, and compliance awareness.

KhoCAR’s Lowbed Trailers UAE service is built for heavy and oversized equipment such as excavators, bulldozers, loaders, cranes, generators, industrial machinery, and project cargo. For teams that need broader fleet support, KhoCAR also provides Truck Rental UAE and related heavy-equipment support services.

Because many lowbed moves are connected to oilfield, construction, and industrial operations, KhoCAR’s wider service ecosystem can also help when equipment needs inspection, preparation, or support before transport. For example, contractors moving machinery from a yard to a site may also benefit from construction machinery repair and maintenance or oilfield teams may need support connected to oilfield services in Abu Dhabi.

Need a Lowbed Trailer Move Planned Around Abu Dhabi Truck Timings?

Moving heavy equipment through Abu Dhabi requires more than a trailer and a driver. You need the right timing window, the right route, the right trailer, the right documentation, and a team that understands how restricted roads, permits, and site access affect lowbed transport.

If you are moving construction machinery, industrial equipment, generators, oilfield equipment, or oversized cargo, KhoCAR can help plan and arrange a safe, compliant lowbed trailer move across Abu Dhabi and the UAE. Explore KhoCAR’s Lowbed Trailers UAE service or contact KhoCAR to discuss your pickup location, cargo details, timing window, and delivery requirements.

FAQs

What are Abu Dhabi truck timings in 2026?

For Abu Dhabi City, heavy vehicles are restricted Monday to Thursday from 6:30am to 9:00am and 3:00pm to 7:00pm. On Friday, the restricted periods are 6:30am to 9:00am and 11:00am to 1:00pm, according to the official DMT Administrative Decision No. 5 of 2025.

Are lowbed trailers allowed in Abu Dhabi during the day?

Lowbed trailers may operate outside restricted heavy-vehicle timings if the route, permit status, cargo dimensions, and road restrictions allow it. However, some roads have specific heavy-vehicle bans or peak-hour limits, so daytime movement must still be checked against current route rules and signage.

Which Abu Dhabi roads are restricted for trucks?

Public announcements identify Sheikh Maktoum bin Rashid Road (E11) and Al Raha Beach Road (E10) as restricted for heavy vehicles from December 1, 2025. Al Rawdah Road/E30 in Musaffah also has peak-hour truck restrictions on a defined segment, with alternatives mentioned through E75, Al Haffar Road, and ICAD Bridge depending on the route.

Do I need a permit for a lowbed trailer move in Abu Dhabi?

A permit may be required if the move involves prohibited areas, restricted corridors, heavy equipment, oversize dimensions, unusual timing, or authority-controlled routes. The official starting point is TAMM’s Issue Mobility Permit of Heavy Vehicle service.

What is the best time to move heavy equipment in Abu Dhabi?

The best time depends on the pickup point, delivery point, route, permit, cargo type, and site access window. In general, planners should avoid the official restricted periods and leave enough buffer before the next restriction starts. For Friday moves, remember that the second restriction is 11:00am to 1:00pm.

Can trucks use E11 in Abu Dhabi?

Do not assume E11 is available for heavy vehicles. ITC announced a heavy-vehicle ban on Sheikh Maktoum bin Rashid Road (E11), with alternative heavy-vehicle routes identified publicly. Always confirm current signage, permit conditions, and authority guidance before planning a lowbed trailer route that touches E11.

What information is needed to book a lowbed trailer in Abu Dhabi?

You should provide the cargo type, weight, dimensions, pickup and delivery locations, site access details, loading method, required delivery date, and any permit or timing constraints. The more accurate the information, the easier it is to select the right trailer and route.

How can I avoid lowbed trailer delays in Abu Dhabi?

Start with cargo measurements, then check the trailer configuration, Abu Dhabi truck timings, restricted roads, permit requirements, site access, and return route. Work with a provider experienced in lowbed trailer route planning and heavy equipment transport so the move is planned around real operating conditions.

Final Compliance Note

This guide summarizes publicly available rules and planning considerations as of 2026. Abu Dhabi transport rules, road signage, permits, and authority instructions can change, and individual moves may have special conditions based on cargo, route, destination, security requirements, or police instructions. Always confirm current requirements through official channels such as DMT, Abu Dhabi Mobility/ITC, TAMM, Darbi, and site-specific transport coordinators before dispatch.